Andersen Corp. and its affiliate, Eagle Window & Door Manufacturing Inc., sued an automated equipment manufacturer after it allegedly failed to design and deliver automated machines intended to produce Andersen Windows E-Series products at Eagle’s Dubuque, Iowa, facility.
The lawsuit was filed in late September in Minnesota’s Washington County District Court against Ontario-based ATS Corp. and its United States-based subsidiary, ATS Ohio Inc. The plaintiffs argue that ATS’ poor project management resulted in continuous delays, design flaws, reworks and extra expenses.

According to the lawsuit, Andersen contacted ATS in 2020 to design and build automated equipment to assemble its E-Series product line at Eagle’s Iowa facility. In preparation for the installation, Eagle officials cleared floor space, re-engineered workflows, dedicated people and capital to meet a carefully sequenced launch, court documents say. Plaintiffs allege that ATS failed to even finish the machines, leading them to pour “millions of dollars into attempting to obtain the equipment that the defendants once promised to provide.”

The lawsuit alleges that ATS “cycled inexperienced personnel through the project, employed flawed processes and performed rework that never brought the equipment to contract compliance. Deadlines were missed by enormous margins—presently the project is more than 860 days behind the original schedule—and ATS is nowhere near meeting contractual requirements.”

The plaintiffs allege that instead of fixing its failures, “ATS shut down work entirely and demanded amendments and millions in extra payments that the contract does not allow. [The] defendants’ conduct has been so egregious as to constitute gross negligence or willful misconduct.”

Plaintiffs claim they have spent the past few years attempting to obtain the missing machines. However, in March 2025, they learned that ATS ended work on the orders, instead transferring resources to other projects. The plaintiffs state that ATS admitted several times that it stopped working on the equipment and refused to move forward unless further amendments or payments were made.

“ATS became so unwilling to continue its flailing attempts to perform its contractual obligations that it resorted to openly welcoming Eagle to terminate the parties’ contract for breach—undoubtedly hoping to obtain additional payment in the process without the need to attempt to perform any further,” the plaintiffs write in court documents.

They claim that, because of ATS inability to provide the machines, they have suffered significant economic losses. To recoup their investment, the plaintiffs seek awards for lost profits, direct, consequential and incidental damages, as well as all other damages resulting from ATS’ breach and repudiation.