Door and Window Manufacturer Magazine Subscribe to the DWM Newsletter

DWM Original StoryIndustry Representatives Meet to Discuss Complex Issue of Exterior Side-Hinge Door System Testing

Specially selected members of the industry's leading associations, along with component suppliers, product manufacturers and pre-hangers gathered on Tuesday in an attempt to resolve the issues surrounding compliance of exterior side-hinged entrance doors with AAMA/WDMA/CSA 101/I.S.2/A440-08 performance requirements.

The meeting of the Door Component Interchangeability Task Group was hosted by the American Architectural Manufacturers Association (AAMA) and the goal was to provide a forum for industry dialogue on the development of component substitution for door certification and testing.

Though advertised as an open forum, AAMA did control access to the meeting by limiting its attendance to those with substantive knowledge of door components and finished product performance. The meeting began by reviewing component testing conducted to date by its task group. It was agreed that the base exterior side-hinged door system should be tested to the air-water-structural requirements as outlined in AAMA/WDMA/CSA 101/I.S.2/A440, NAFS - North American Fenestration Standard/Specification for windows, doors, and skylights. Based upon this testing, component substitution would be permitted per the specific test requirements as applicable within this document. In addition, participants of the door forum discussed a pure component-based testing and qualification method and agreed that complete component mixing deserved additional study.

Jeff Lowinski, vice president, Advocacy and Technical Services for the Window and Door Manufacturers Association and Mark Fortun, manager of testing and certification for Endura Products in Colfax, N.C., and chairman of the task group, were a few of those in attendance, along with representatives from the Association of Millwork Distributors.

In essence, the meeting was very positive, according to Lowinski, who says there were a lot of viewpoints represented.

"The intention [in my mind] was to get all players to talk and come up with a consistent and uniform set of guidelines [or positions] regarding this issue," he says.

"The group discussed initial system testing that will be necessary before components can be substituted. Not every configuration will necessarily need to be tested, nor will every component substitution require a system test, but there is a need for a documented trail that supports any combination of components back to testing or reliable engineering evaluation," he adds.

Fortun is also optimistic about the meeting's turnout.

"I was very encouraged by the cross-section of the door industry that attended the meeting and the openness and positive contribution by all of those in attendance toward the development of a component interchangeability guideline… regardless of the company each attendee represented, all agreed on the importance of having a solution which addressed the needs of the pre-hanger segment. There was also agreement that such a solution will be beneficial to the door industry overall. I'm very encouraged by the unison within the group." Fortun says.

He also feels progress was made during the meeting.

"Prior to the meeting some of the initial documents that will likely be incorporated into the guideline were drafted by Jeld-Wen and Endura. These facilitated input and suggestions by the wider group and helped generate early momentum in the meeting," Fortun explains. "However, this was only the first meeting and there is considerable work ahead as we continue to draft out remaining portions of the guideline and then validate feasibility. With depth and breadth of those attending, I expect positive progress."

Another door forum is expected to take place on September 25 following the AAMA National Fall Conference in San Antonio, and Lowinski says that although progress has been made there are a great deal of issues that need to be discussed.

"We haven't even touched on a lot of the components," he says.

Fortun says that the actual approach to component interchangeability is not yet worked out.

"We are evaluating if the guideline will require some baseline system testing, coupled with component evaluation to allow component interchangeability, or if component-only testing can be used. It's still too early in this process to understand what the best solution will be, and will require further discussions (at our future meetings). Regarding door failures, this was just a generic discussion on what those attending have experienced in the market, whether it is in coastal or non-coastal areas."

Lowinski says that the work this group does will aid in preparation for the 2012 code cycle. "The goal is to have 'guideline' work completed for reference by industry certification programs in time for the 2012 ICC code cycle," he says.

Need more info and analysis about the issues?
CLICK HERE to subscribe to DWM magazine.